1. 350vip浦京集团




      1. CORREN POSITION: HOME1 > NEWS CENTER > Picture News

        Unit-1 of Philippines Puting Bato 1x135MW Coal-Fired Power Plant Project Finished the Reliability Test Run Successfully

        Source : Author: Date :2014-10-27【Font :B M S


        At 17:00 on Oct. 27, Unit-1 of Philippines Puting Bato 1x135MW Coal-Fired Power Plant Project contracted by CNTIC finished the reliability test run successfully. The Owner, the contractor and CNTIC signed the test documents.




        1. XML地图