1. 350vip浦京集团




      1. CORREN POSITION: HOME1 > NEWS CENTER > News

        Unit-2 in 2×660mw Super Critical Coal Fired Thermal Power Project Contracted by CNTIC Has Finished in Covering the HP-Cylinder and IP-Cylinder of the Steam Turbine at the First Try

        Source : Author : Date:2016-07-05【Font :B M S

        At 11:30 on July 3, 2016 India local time, Unit-2 in 2×660mw Super Critical Coal Fired Thermal Power Project Contracted by CNTIC has finished in covering the hp-cylinder and ip-cylinder of the steam turbine at the first try. Thus all the milestone of unit-2 have been achieved and laid a solid foundation for final taking over.